| Phase | Triggering Event | Regulatory Deadline | Required Operational Record |
|---|---|---|---|
| Initial Payment or Denial | Submission of a clean claim by the provider | 30 calendar days From the date the plan receives the clean claim. | Initial Payment/Notice of Denial, EOB/ERA, and QPA Disclosure. |
| Initiate Open Negotiation | Receipt of initial payment or notice of denial | 30 business days From receipt date. | Standard Open Negotiation Notice and proof of delivery/receipt. |
| Open Negotiation Period | Submission of the Open Negotiation Notice | 30 business days Duration of the negotiation period. | Log of all offers, counteroffers, and related correspondence. |
| Initiate Federal IDR | Exhaustion of the 30-business-day open negotiation period without agreement | 4 business days Following the end of the negotiation period. | Notice of IDR Initiation (via CMS portal) proposing a certified IDR entity. |
| IDR Entity Selection | Receipt of the Notice of IDR Initiation | 3 business days For the non-initiating party to object or agree. | Notice of agreement or alternative entity proposal. |
| Submit Final Offers | Selection/assignment of the certified IDR entity | 10 business days From the date the entity is finalized. | Notice of Offer, final requested payment amount, and indexed evidentiary packet (acuity, QPA disputes, etc.). |
| Payment Determination | Selection/assignment of the certified IDR entity | 30 business days For the entity to issue a binding determination. | Written decision from the certified IDR entity. |
| Final Payment | Issuance of the binding IDR determination | 30 calendar days From the determination date. | Remittance advice reflecting the final determined amount. |
Disclaimer: This matrix provides general federal timeframes for operational reference. Actual deadlines may vary due to weekend/holiday calculations, CMS administrative extensions, disaster relief pauses, or the application of a specified state law. Always verify current timelines directly on the CMS NSA portal.